Upcoming Bid Packages:
The Life Sciences Public Health Laboratory project will provide multiple opportunities for participation in the project. The schedule below is a guide to the timing of procurement activities. This page will be updated with actual bid dates when available.
Bid Release #1 – September 9, 2024
Design Assist RFQ
23A HVAC Wet Central Utility Plant (CUP)/ Core and Shell (C&S) - Part A
23C HVAC Dry Central Utility Plant (CUP)/ Core and Shell (C&S) - Part A
26A Electrical Central Utility Plant (CUP)/ Core and Shell (C&S) - Part A
22A Plumbing Central Utility Plant (CUP)/ Core and Shell (C&S) - Part A
23E Controls
Bid Release #2 – December 2024
26D Electrical UG to OGS Substation
31A Mass Excavation
33A Site Utilities
26C SB - Emergency Generators
26G SB - Emergency Electrical
Equipment
26H SB - Normal Electrical Equipment
23I SB/xPL - Modular Air Source Heat Pump (ASHP) Platform
Bid Release #3 – May 2025
05A Structural Steel
08C Exterior Glazing
08D Exterior Metal Panel
14A Elevator
03A Concrete Foundations & SOG
07D Fire Proofing
03B Concrete SOMD & Fill at Stairs
07C Waterproofing
11B Window Washing Equipment - VOID
Bid Release #4 – October 2025
03C Precast Wall Panels - VOID
04A Masonry
05B Exterior Backup Wall/Sheathing
07A Roofing
22A Plumbing Underground
23F.1 SB/xPL - HVAC Equipment - ASHP/ACC
23F.2 SB/xPL - HVAC Equipment - AHU/HRU/Humidifier Pumps
23F.4 SB/xPL - HVAC Equipment - HVAC Fans & VFDs
23F.5 SB/xPL - HVAC Equipment - Boilers
23F.6 SB/xPL - HVAC Equipment - Clean Steam Generators

Bid Release #5 – March 2026
06A Millwork & Casework
05C Misc. Metals
07F Firestopping
08B Interior Glazing
08E Demountable Partitions
09A Framing & Drywall Core & Shell
09B Framing & Drywall Interior Fitout
09C Acoustical Ceiling
10A FRP Wall & Ceiling Panels
11A Residential & Foodservice Equipment
11C SB/xPL - Lab Equipment Environmental Rooms
11D SB/xPL - Lab Equipment Bio Safety Cabinets
11E SB/xPL - Lab Equipment Fume Hoods
11F SB/xPL - Lab Equipment Autoclaves
11G SB/xPL - Lab Equipment Refrigerators & Freezers
11H SB/xPL - Lab Equipment Misc.
12B SB/xPL - Laboratory Casework
21A Fire Protection
22B Plumbing CUP/C&S (Domestic Water, Compressed Air)
22C Plumbing Program Areas
22D Plumbing CUP/C&S (Sanitary)
22E Plumbing CUP/C&S (Siphonic Rainwater Drain System)
22G Plumbing Heat Pump
23B HVAC Wet Fitout
23D HVAC Dry Fitout
23J Air Terminal Units
26B Electrical Program Fitout
26E Exterior Lighting and Controls
26F Exterior Lighting/Controls/Charging Stations
26J Light Fixtures (Furnish Only)*
27A Tel/Data Core & Shell
27B Tel/Data Program Fitout
27C Audio/Visual Equipment & Systems
27D Security System & Access Control
28A Security & Fire Alarm
Bid Release #6 – June 2026
08A Doors/Frames/Hardware
08D Overhead Coiling Doors - VOID
13A Radiation Shielding -VOID
09D Flooring - VCT, Carpet, Resilient
09E Painting & Wallcovering
09F Resinous Flooring
09G Epoxy Terrazzo
09H Ceramic Tile
10B Interior Signage
10C Interior Specialties
10D Wall & Door Protection
32A Exterior Improvements
12A Window Treatment
GC/GR Packages
GC09 Security Cameras
GC10 Site Camera – Timelapse
GC12 Construction Progress Photos
GC17 Equipment Rental
GC18 Final Cleaning
GC26 Owner Video Training
Prequalification Process for the Life Sciences Public Health Laboratory
*All 2nd Tier subcontractors and suppliers are not required to submit prequalification information.
Prime/Tier-1 Contractors will be selected to participate in the prequalification process from the businesses submitting the Contractor Interest Form. Prime/Tier 1 contractors will be required to be prequalified to submit a proposal.